Estimation and Costing MCQ Set-1 Question 1:-


While estimating for plastering, usually no deduction is made for

(a) ends of beams
(b) small openings upto 0.5 sq. m
(c) end of rafters
(d) all the above

Ans: (d) all the above ✔

Estimation and Costing MCQ Question 2:-


In absence of detailed design the percentage of steel in concrete columns is usually taken as

(a) 10 to 15 percent
(b) 5 to 10 percent
(c) 1 to 5 percent
(d) 15 to 20 percent

Ans: (c) 1 to 5 percent

Estimation and Costing MCQ Question 3:-


Which one is overhead items. expenditure of the following

(a) Rent and taxes
(b) Establishment charges
(c) Office stationary items
(d) Workmen’s compensation

Ans: (d) Workmen’s compensation ✔

Estimation and Costing MCQ Question 4:-


A revised estimate is prepared if the sanctioned estimate exceeds

(a) 2%
(b) 5%
(c) 8%
(d) 10%

Ans: (b) 5% ✔

Estimation and Costing MCQ Question 5:-


In a detailed estimate the provision for contingencies is, usually

(a) 1%
(b) 3% to 5%
(c) 10%
(d) 12% to 50%

Ans: (b) 3% to 5% ✔