Home >> Estimation and Costing MCQ Set-1
Estimation and Costing MCQ Set-1 Question 1:-
While estimating for plastering, usually no deduction is made for
(a) ends of beams
(b) small openings upto 0.5 sq. m
(c) end of rafters
(d) all the above
Estimation and Costing MCQ Question 2:-
In absence of detailed design the percentage of steel in concrete columns is usually taken as
(a) 10 to 15 percent
(b) 5 to 10 percent
(c) 1 to 5 percent
(d) 15 to 20 percent
Estimation and Costing MCQ Question 3:-
Which one is overhead items. expenditure of the following
(a) Rent and taxes
(b) Establishment charges
(c) Office stationary items
(d) Workmen’s compensation
Estimation and Costing MCQ Question 4:-
A revised estimate is prepared if the sanctioned estimate exceeds
(a) 2%
(b) 5%
(c) 8%
(d) 10%
Estimation and Costing MCQ Question 5:-
In a detailed estimate the provision for contingencies is, usually
(a) 1%
(b) 3% to 5%
(c) 10%
(d) 12% to 50%